Problem Definition Tree:
CTQ Drill down or Problem Definition Tree diagram relates high level focal points(Resultant output)to project objective(factors)
The measure of those items linked to the CTQ are called Project Y.
The following situations mandates the Problem definition Tree to be applied:
1.When Project Indication is vague without knowing which parameter need to be improved.
2.When parameters of Big Ys are defined from customer perspective rather than process control perspective.
3.When dimensions of the Big Ys are aimed at abstract terms and not in tangible terms.
In General ,The following rules can be applied while splitting the Big Ys to Project Y :
1st Rule – Boxes in a split should not overlap. Need to respect the parent dictionary and divide it into subgroups
2nd rule – Need to ensure that sub groups selected must encompass the whole dictionary .
3rd Rule – Boxes or sub groups must be able to provide us with details and data needed for running experiments.
The Black belt should finalize the last unbreakable activity or component which can contribute to the Big Y and select this item as Project Y. This is the actionable item which need to be acted upon to improve the Project Y and thus the Big Y to solve
Let us take example of OEE Overall Equipment efficiency not achieved the Target for may '23( Big Y) and drill down to find the project Y - which contributes the highest , so that action can be initiated immediately .
The injection molding machine shop OEE is 84% , which is average of 3 machines OEE #1,#2,#3.However target is 90%.
In this Example - the black belt has to stop here and take a call, after he had broken down the Big Y to actionable items or factor KPIs, at the activities contributing to availability loss of M/C #2 - out of the which Top 3 activity can be taken as Project Ys .Thus we have divided our Big Y of OEE Target not achieved problem into many Project Ys and Black Belt can stop here as below to finalize projects for further working by small work groups on each .
Here Changeover Time is the 1st actionable item to be worked on followed by Breakdown time reduction & material shortage issue reduction. Once all these Project Ys are addressed , eventually the Big Y ( OEE of molding) would be achieved. Problem definition Tree clearly gives us direction, focus.
1.Change over time - 45%
2.Breakdown Time - 22%
3.Raw material shortage time - 18%
The General criteria/steps to be used while splitting boxes.
1.Use Logic to make splits ( using creative & alternate searches)
2.Never move to next level until , all important in the family is identified.
3.Make Broad splits first and detailed splits later - Avoid going into the factor x , until the detailed split of Ys
4.FInally use facts and physical laws of logical correlation to make decision vis cause/effect matrix.