Logical Relationships (or task dependencies) is a concept in project management that specifies the relationship between project tasks and the order in which they have to be performed. It helps in preparing the project plan. There are 4 kinds of logical relationships:
Start-to-start (SS) – Predecessor task must start before the Successor can start
Finish-to-start (FS) – Predecessor must finish before Successor can start
Start-to-finish (SF) – Predecessor must start before Successor can finish
Finish-to-finish (FF) – Predecessor must finish before Successor can finish
An application-oriented question on the topic along with responses can be seen below. The best answer was provided by Dipankar Acharya and Suresh Sekar.
Applause for all the respondents - Rajender Prasad, Suresh Sekar, Dipankar Acharya