Critical path and Critical chain method:
Both Critical Path and Critical chain methods are types of schedule network diagramming techniques used in developing the project schedule.
Critical path is the longest path of schedule network and the duration of critical path is the project duration. Floats are calculated, based on difference between critical and non critical pathway. Free float can be defined as the amount of time an activity can be delayed, without any delay in the successor activity. Total float can be defined as amount of delay in the activity that can be done, without affecting the overall project duration. Floats in all critical path activities are zero.
Critical chain is modification of critical pathway with resource optimization. Based on resource availability schedule is prepared. Here buffers are used instead of float. Buffers account for contingency. Buffer is not zero in critical chain pathway. There is no early and late start or early and late finish. There can be only one start and one finish.
The Project Buffer is the total buffer at the end of the project. Any delayed activity can consume this buffer.
The Feeding Buffer is the buffer added to non critical chain , so that these non critical chain, if delayed, can use this buffer.
The Resource Buffer is a resource kept as buffer along critical chain, so that continuity of the work is ensured.
Differences Between Critical Path and Critical Chain Method
Resources
The critical path method does not assume any resource constraint and assumes that it is freely available. The critical chain method, on the contrary assumes resource constraint and builds a realistic schedule based on availability. Critical chain based method schedule may be of longer duration, but is more realistic.
Float/Buffer
In the critical path method, float can not be utilized before the early start of succeeding activity. While in case of critical chain, if preceding activity gets finished early, succeeding activity can be started earlier and time saved will be added to project buffer.
Misuse of Float
In the critical path method, team members often do not start an activity, until they utilize the float of the activity completely, till late start. Where as in critical chain, each activity has a realistic schedule and time gained is placed at the end of project as project buffer.
Project progress: Floats can not be used to assess project progress, where as buffers can be used to analyze project progress.
Critical path method:
Critical Chain method:
Correlation of Critical chain with lean and theory of constraints:
Lean management aims at value creation over entire processes of organization, where as critical chain and theory of constraints are centered on managing time duration and uncertainties of the project. The uncertainties of durations and project completion can be contributed to inadequate management processes, which can be sorted by lean management practices.
Lean practice implementation has greater effect on correcting processes unevenness, eliminating wastes and have more impact on whole organization, whereas critical chain and theory of constraint methods are efficacious in task completion on time and project monitoring, by optimizing the resource constraint.
Images Sources:
Critical Path:
www.blog.pmsprout.com
Critical Chain:
www.blog.pmsprout.com