Cycle Time - Time spent in specific task for one unit – commonly presented as hours per unit. (or minutes per unit). It is calculated as the time spent between start and end of a specific task for one unit. Each step within a process will have its own cycle time.
Takt Time - Takt is derived from a German word Taktzeit, meaning clock interval, pulse or beat. It is the concept that all activity within a business is synchronized by a beat, set by the customer demand. In other words, it is the production rate at which one unit should be produced or serviced in order to meet the customer demand. Takt Time is calculated as Total Available Time divided by the Customer Demand
E.g. Customer demand is 16 products in a day. Assuming the working window is 8 hours, the Takt Time = 8/16 = 0.5 hours = 30 minutes. This implies that in order to meet the customer demand of 16 products a day, one unit should be produced every 30 minutes.
Overall Equipment Effectiveness (OEE) is a lean metric to assess the actual performance of a production line compared to its maximum potential. It is represented in percentage terms.
OEE = Quality x Productivity x Availability.
Quality considers the good parts, Productivity considers the rate of production and Availability considers stoppage time.
An application-oriented question on the topic along with responses can be seen below. The best answer was provided by Johanan Collins on 6th Mar 2022.
Applause for all the respondents - Johanan Collins, Priyanka Bose, Shiva Kumar V, Ramjanam Singh.