6 Big Losses are the most common productivity losses (in a plant) caused due to the equipment. The 6 losses are
- Equipment Failure
- Setup and Adjustments
- Idling and Minor Stops
- Reduced Speed
- Process Defects
- Reduced Yield
The concept is a part of Total Productive Maintenance (TPM) and was developed by Seiichi Nakajima.
An application-oriented question on the topic along with responses can be seen below. The best answer was provided by Shashikant Adlakha on 7th February 2020.
Applause for all the respondents - Shashikant Adlakha, Manish Gupta and Sudheer Chauhan.
Also review the answer provided by Mr Venugopal R, Benchmark Six Sigma's in-house expert.